Wrap Report Guide: Closing Out a Film Production Step by Step

Spencer KaufmanBy Spencer KaufmanSeptember 14, 20266 min read

Quick answer

A wrap report closes the shoot on paper. It compares scheduled and actual days, scenes, pages, and setups from the final production report, lists overages like meal penalties and added days, and collects each department's close-out: rentals returned, loss and damage, purchases kept or sold, and deposits recovered. It also records shots still owed to post and where every piece of paperwork is filed.

On this page
  1. The order of work
  2. Step 1: the schedule numbers
  3. Step 2: the labor and incident summary
  4. Step 3: department close-outs
  5. Step 4: locations and deposits
  6. Step 5: what post needs to know
  7. Step 6: the paperwork archive
  8. Mistakes that make a wrap report useless
  9. Storiara at wrap

The last shot of principal photography isn't the end of the production office's work. Trucks go back, lenses get checked for scratches, the location owner walks the house looking for damage, and the accountant waits on invoices. The wrap report is where all of that ends up in one document, so a producer, a financier, or a post supervisor can see what happened without calling eight people.

The wrap report glossary entry covers what the document contains. This guide is about how to produce one, in order, using a fictional 20-day feature called MILE MARKER. Use the wrap report template for the layout.

The order of work

A wrap report written in one sitting three weeks after wrap is mostly guesses. Break it up by when the information exists.

WhenWhat to collectFrom
Last shoot day, at wrapFinal production report with to-date totals2nd AD
Wrap days (usually one to several days per department)Rental return slips, damage notes, purchases keptEach department head
Before department heads' final daySigned department close-out sectionsEach department head
First week after wrapLocation walk-throughs, deposit status, vehicle returnsLocations, transportation
First weeks after wrapOpen invoices, loss and damage invoices, insurance claimsProduction accountant
Once post has viewed the footageShots still owed, pickup day planPost supervisor, 1st AD, director

The hard deadline is the department heads' last day. A gaffer who has moved onto another show will answer a question about a missing cable, eventually. Get the close-out section signed while they're still on your payroll.

Step 1: the schedule numbers

Start from the final daily production report. Its "total to date" lines already contain most of what you need.

ScheduledActualVariance
Shoot days2021+1 (Day 21 added for Sc. 57, 58 after Day 9 was lost to wind)
Scenes128127Sc. 102 omitted in pink revisions
Pages9695 1/8-7/8 (Sc. 102)
Average pages per day4 6/84 4/8
Setups812

Show the arithmetic so anyone can check it. 96 pages is 768 eighths. Scene 102 was 7/8 of a page, so 768 - 7 = 761 eighths shot, which is 95 1/8 pages. Divided over 21 days, 761 eighths is about 36.2 eighths a day, or roughly 4 4/8 pages. The scheduled average was 768 over 20 days, 38.4 eighths, or about 4 6/8.

Put the reason for each variance on the same line. "+1 day" means nothing to a completion guarantor. "Day 9 lost to wind, Sc. 57 and 58 moved to added Day 21" tells them it was weather, which may matter to insurance.

The daily production report guide explains where each of those to-date numbers comes from.

Step 2: the labor and incident summary

Pull these from the daily reports and the hot cost reports, not from memory.

ItemMILE MARKER
Days over 12 hours5 (Days 3, 9, 14, 15, 18)
Days with meal penalties6, totals by day from hot costs
Forced calls1, Day 15, one performer
Weather daysDay 9 (wind), cover set not available
Company moves7
Accidents and injuriesDay 11: set PA, sprained ankle at base camp, first aid on set, clinic visit. Workers' comp claim filed 10/23
Property damageDay 17: scuff on hallway paint at the Ferris house, repaired by production 11/4
Pickups owedSc. 91 insert (badge on dash). See Step 5

Each incident line has a date, what happened, and what was done about it. Insurance and the accountant both need the claim dates. Leave dollar amounts to the accountant's section unless the number is final.

Step 3: department close-outs

Send every department head the same short form early in the last week, and ask for it back on their last wrap day:

  1. Rentals: every item returned, the date, who signed the return slip, and any damage the rental house noted.
  2. Purchases: what was bought, what is being kept (and for what), what was returned for credit, sold, or donated.
  3. Loss and damage: anything lost, broken, or missing, with the date it happened.
  4. Open items: anything still out, with an owner and a date.
  5. Signature and date.

A single loss and damage line from camera on MILE MARKER reads: "1x 50mm prime, chipped front element, noticed at check-in by rental house 11/2, likely Day 19 (car rig). Rental house quote pending." Notice what it doesn't say. Nobody has guessed a dollar amount yet, and the date is marked as likely. The accountant adds the invoice amount when it arrives.

Departments with the most to report are usually camera, grip and electric, art (set dressing and props), wardrobe, locations, and transportation. Wardrobe and props should list what's being held for pickup shots or reshoots, because those items can't be sold or returned yet.

Step 4: locations and deposits

Every location gets a line: date of the final walk-through, who attended for production and for the owner, any damage claimed, the status of the security deposit, and a signed release of claims if your location agreement uses one. The location agreement spells out what production promised to restore.

On MILE MARKER, the Ferris house walk-through found the hallway scuff. Production repainted it, the owner signed off on November 4, and the deposit came back. The ranch location's owner reported ruts on the road from the Day 14 water truck, and that line stays open with the location manager as owner until it's resolved.

Step 5: what post needs to know

The editor will find missing coverage eventually. The wrap report should tell post first. List every owed shot with its scene, what's missing, whether it needs cast, and what's being held for it.

Sc.OwedCastHeld itemsPlan
91Insert: sheriff badge on dashboardNoneBadge (props), sheriff unit booked through vendorSecond unit half day, date TBD with post

If nothing is owed, write "No owed shots per script supervisor's final notes" and attach those notes. A blank section looks like nobody checked.

Step 6: the paperwork archive

Say where every document lives. Somebody will need an Exhibit G or a location release years from now, and the wrap report is where they'll look first.

DocumentWhere filed
Call sheets (final sent version per day)Production drive, /Paperwork/Call Sheets
Daily production reports, signedProduction drive and originals in box 1
Exhibit Gs, signedOriginals in box 1, copies with payroll
Crew time cardsPayroll company, copies in box 2
Talent and location releasesProduction drive, originals in box 3
Permits, certificates of insuranceProduction drive, /Legal
Camera, sound, and script supervisor reportsProduction drive and with post
Accident and incident reportsProduction drive, /Insurance

Crew time records have legal retention rules. California's wage order for the motion picture industry, for example, requires time records showing when each work period begins and ends, and says required records must be kept on file for at least three years. Other states, unions, and financiers have their own requirements, so ask the payroll company and production counsel which apply to your show, and note them here.

Mistakes that make a wrap report useless

Writing it from memory. If the numbers don't trace back to a signed production report, nobody can rely on them.

Collecting department sections late. The information is still there, spread across people who have stopped answering email.

Hiding the variances. A wrap report that shows 20 scheduled days and 21 actual days without saying why invites the question anyway, usually from someone who's paying for the extra day.

Listing returns without return slips. "Returned" with no signature is how a rental house bills you for a light you gave back.

Ending the report without owners. Every open item needs a person and a date, or it stays open indefinitely.

Storiara at wrap

Storiara doesn't track actual costs, returns, or deposits, so the wrap report itself is built outside it. It can print a full project (locations, cast and crew, assets, equipment, the shot list, and the schedule) and export the budget to Excel, which gives the archive a record of what was planned to compare against the final cost report.

Frequently asked questions

Who writes the wrap report on a film?

The UPM or line producer owns it. The 2nd AD supplies the schedule numbers from the final production report, each department head writes their own close-out section, and the production accountant adds the cost figures and open invoices.

When is the wrap report due?

It depends on the production and its financiers, but the department sections should be collected before crew finish their wrap days and final paychecks go out. After that, people move to other jobs and details get lost.

What's the difference between a wrap report and a daily production report?

The daily production report covers one day. The wrap report summarizes the whole shoot, using the last day's to-date totals, and adds everything that happens after the camera stops: returns, loss and damage, deposits, and owed shots.

Does the wrap report replace the final cost report?

No. The final cost report is the accounting document that closes the budget. The wrap report explains the production side behind it, such as why a day was added or a lens was billed, and it's usually finished before the last invoices arrive.

Sources

Plan your production in Storiara

Upload a PDF, Word, or Final Draft script. Storiara breaks it down into scenes, cast, locations, props, and wardrobe, and keeps the stripboard, budget, and call sheets tied to that breakdown.

Start Planning for Free
Spencer Kaufman

Spencer Kaufman

Revenue & Strategy Lead, Storiara

Revenue and strategy expert growing Storiara's market presence and building partnerships with filmmakers and studios worldwide.