Wrap Report Template for Film Production (Free XLSX, CSV, PDF)

Spencer KaufmanBy Spencer KaufmanSeptember 14, 20264 min read

What this template is for

A wrap report is the document the UPM or line producer puts together when shooting ends. It compares scheduled and actual shoot days, scenes, and pages, lists overtime and meal penalties, and records location sign-offs, equipment returns, loss and damage, incidents, and open items so accounting can close the show. This template is filled in for a 12-day indie feature.

On this page
  1. What each section is for
  2. Building the report, in order
  3. Mistakes that make the report useless
  4. How it connects
  5. Wrap tasks in Storiara

Download the template

Free, no email required. The example rows use a fictional production so you can see how each field is filled in.

Preview

PRODUCTION WRAP REPORT

Header

FieldValue
ProductionSALT FLATS
CompanyDry Creek Pictures LLC
Principal photographyMon 10/5/2026 to Sat 10/17/2026
Schedule compared againstOne-line, Blue, 9/29/2026
Prepared byRosa Delgado, line producer / UPM
Date preparedFri 10/23/2026

Summary

MeasureScheduledActualVarianceNote
Shoot days12120
Scenes44440
Pages70700Sc. 44 moved from Day 10 to Day 11
Average pages per day5 7/85 7/8070 / 12 = 5.83
Days over 12 hours, crew call to wrap5Days 2, 4, 5, 8, 11
Cast meal penalties0None on any Exhibit G
Company moves110Day 4

Day by day

DayDateLocationSched. pagesActual pagesCrew call / wrapNotes
1Mon 10/5Ruiz House, Oildale5 7/85 7/87:00 AM / 6:45 PM
2Tue 10/6Ruiz House, Oildale6 1/86 1/87:00 AM / 7:10 PM
3Wed 10/7Hardesty Salvage667:00 AM / 6:30 PM
4Thu 10/8Hardesty Salvage, move to Tumbleweed Diner6 7/86 7/87:00 AM / 7:40 PMCrusher delayed first shot 14 min. Lunch 12:45 PM, no meal penalties.
5Fri 10/9Sundown Motor Inn6 2/86 2/87:00 AM / 8:00 PM13 hours. Tenting for Sc. 23, 24 took 90 min.
6Sat 10/10Sundown Motor Inn, Union Ave5 2/85 2/84:00 PM / 3:50 AM
7Mon 10/12Gas station, Buttonwillow5 1/85 1/87:00 AM / 6:20 PM
8Tue 10/13Hwy 58, county roads6 3/86 3/87:00 AM / 7:30 PMProcess trailer
9Wed 10/14Warehouse set, Bakersfield5 6/85 6/87:00 AM / 6:15 PM
10Thu 10/15Salt flats, private ranch64 3/87:00 AM / 7:00 PMWind held the 12x12 down 2 hrs. Sc. 44 (1 5/8) lost sunset, moved to Day 11.
11Fri 10/16Salt flats, private ranch5 5/87 2/810:00 AM / 10:30 PM12.5 hours. Sc. 44 added before Sc. 42.
12Sat 10/17Orchard Road, Shafter4 6/84 6/84:00 PM / 2:40 AMPicture wrap 2:10 AM
TOTAL7070

Cast and background

ItemScheduledActualNote
Cast paid days (DOOD)4747No added days
Stunt days66S1, S2, S3 rehearsal Day 10, work Day 11
Background days10106 on Day 4, 4 on Day 6. 10 releases on file.

Locations

LocationWalk-throughConditionMoneyStatus
Ruiz House, Oildale10/7No damageFee paid in fullClosed
Hardesty Salvage10/9No damageSecond payment $1,150 released 10/9Closed
Tumbleweed Diner10/9Booth bench scuffed, repaired by art dept 10/12Fee paid in fullClosed, owner signed off
Sundown Motor Inn10/11No damageDeposit returnedClosed
Gas station, Buttonwillow10/12No damageFee paid in fullClosed
Salt flats, private ranch10/19Tire ruts on access road, regraded 10/19Fee paid, regrading invoice pendingOpen
     

Equipment returns, loss and damage

DeptItemReturnedIssueStatus
CameraFull A-cam package10/19Salt dust on matte box and legs, vendor cleaningCleaning invoice pending
CameraB-cam body (Day 11)10/19NoneClosed
Grip4x4 floppy (1)10/19Torn in wind, Day 10Replacement invoice pending
SoundDPA 4060 lav (1), mixer's kitn/aLost Day 7Claim per deal memo, open
ProductionWalkies19 of 201 radio and headset missingOpen, checking vans
     
     

Incidents

DayWhat happenedActionReport filed
10Grip pinched hand in 12x12 frame cornerTreated by set medic, returned to workYes, 10/15
    

Open items

ItemOwnerDue
Final G&E and camera invoicesProduction accountant10/30
Ranch access road regrading invoiceLocation manager10/30
Lav claim and missing walkieProduction coordinator10/28
ADR for Sc. 26 (Pace), traffic noise on Union AvePost supervisorBefore sound mix
Camera original media: 2 RAID copies verified, shuttle drive to editorDITDelivered 10/19
   
   
   

Sign-off

NameTitleSignatureDate
Rosa DelgadoLine producer / UPM
Sam WhitfordProducer

Template by Storiara (storiara.com). Free to use and modify.

SALT FLATS finished on schedule in the headline numbers: 12 days, 44 scenes, 70 pages. The day-by-day table shows it wasn't that tidy. Day 10 lost 1 5/8 pages to wind and a missed sunset, Day 11 absorbed them, and five days ran more than 12 hours from crew call to wrap. The report is where that gets written down while people still remember why.

For the definition and who writes which version, the glossary entry on the wrap report covers it. The wrap report guide goes into department wrap notes in more detail. This page is about building the production-wide report from the paperwork you already have.

What each section is for

Summary

The top table answers the question a producer or financier will ask first: did it come in as planned. Scheduled numbers come from the final approved schedule, which is why the header names the version (Blue, 9/29/2026). Actual numbers come from the daily production reports.

Average pages per day is 70 / 12 = 5.83 pages, which rounds to 5 7/8 in eighths (5.83 is closer to 5.875 than to 5.75). It's worth including because the next production with this team will use it to plan.

Day by day

One row per shoot day, copied from each DPR. The pages column should add up and match the summary. The check for SALT FLATS in eighths:

  • Scheduled: 47 + 49 + 48 + 55 + 50 + 42 + 41 + 51 + 46 + 48 + 45 + 38 = 560 eighths = 70 pages
  • Actual: Day 10 drops by 13 eighths (48 to 35) and Day 11 gains 13 (45 to 58). Everything else is unchanged, so the total is still 560 eighths, or 70 pages.

The notes column is for cause, stated briefly. "Wind held the 12x12 down 2 hrs" tells the reader why Day 10 came up short in a way "weather" doesn't.

Cast and background

Cast paid days come from the day out of days. SALT FLATS scheduled 47 and paid 47, because Scene 44 moved to a day when all three performers were already working. If it had moved to a day when Hollis was dropped, the report would show an added paid day and a cost. Background counts are matched against releases on file, which is why the row says "10 releases."

Meal penalties are counted here, and the detail lives on the Exhibit G. SALT FLATS had none. On Day 4, the heaviest day, lunch was called on time at 12:45 PM, and Hollis, Pace, and Bev were each dismissed within six hours of reporting, so none of them needed a meal. For how penalties are calculated, see meal penalties explained.

Locations

One row per location, with the walk-through date, condition, and money status. The Hardesty Salvage row ties back to its location release form, which held back the second $1,150 until the walk-through. Anything with money still owed stays "Open."

Equipment, incidents, open items

Returns and loss and damage come from the equipment checklist In column. The lost lav belongs to the mixer's kit, so it's handled under her deal memo rather than with the rental house. Incidents list every injury or near miss that got a report, even minor ones. Open items each get an owner and a due date, since an item nobody owns tends to sit on the list until the accountant asks about it.

Building the report, in order

  1. Collect every DPR, the final Exhibit G, the DOOD, and the approved schedule version.
  2. Fill in the summary from the schedule, then add actuals from the DPRs.
  3. Copy each day's pages, calls, wraps, and notes into the day-by-day table. Add the eighths and check the totals against the summary.
  4. Get cast paid days from the DOOD and compare with payroll. Count background against releases.
  5. Ask the location manager for walk-through dates and the status of every fee and deposit.
  6. Ask each department for its return count and loss and damage list. Compare against the equipment checklist.
  7. Pull incident reports from the set medic and the production office.
  8. List every open item with an owner and a due date.
  9. Have the UPM and producer review and sign.
  10. Send to the production accountant, then producers and anyone with reporting rights.

Mistakes that make the report useless

Comparing against the wrong schedule. If the actuals are compared to the white draft, every day looks like a variance, and the real problems get lost.

Notes that don't say why. "Behind" on Day 10 doesn't help anyone plan the next salt flat shoot. "Wind, 2 hours" does.

Closing items that aren't closed. The ranch regrading invoice isn't paid, so the row stays open even though the work is done.

Leaving out small losses. A missing walkie becomes a charge on the vendor's final invoice, and if it isn't on the report, the accountant won't know what the charge is.

How it connects

The wrap report is built from the DPRs, and its cost-related items (overages, penalties, damage) feed the final cost report. If you tracked daily overages during the shoot on a hot cost report, use those figures to explain variances here.

Wrap tasks in Storiara

Storiara doesn't produce a wrap report. For the open-items part, each story has a Shared To-Do list where tasks get an assignee and a due date and can be marked complete. The full project (schedule, cast and crew, locations, equipment) can also be printed from My Stories as a record of what was planned. The scheduling feature page shows how the schedule side works.

Frequently asked questions

When is a wrap report due?

Most productions aim to have the production-wide report done within a week or two of the last shoot day, once equipment is returned and locations are signed off. Open items like final invoices can stay listed as pending.

What's the difference between a wrap report and the last daily production report?

The last DPR covers one day. The wrap report totals the whole shoot from all the DPRs and adds the close-out business: returns, deposits, damage claims, and what's still unpaid.

Who gets a copy of the wrap report?

The producers, the production accountant, and any financier or completion guarantor that asked for reporting. Department heads usually get the sections that concern them.

Where do the scheduled numbers come from?

From the final approved shooting schedule or one-line, not the first draft. On this template that's the Blue version of the one-line dated 9/29/2026.

Skip the blank wrap report

Upload your script to Storiara and it breaks down scenes, cast, locations, props, and wardrobe for you. The schedule, day out of days, budget, and call sheets all draw on that breakdown.

Start Planning for Free
Spencer Kaufman

Spencer Kaufman

Revenue & Strategy Lead, Storiara

Revenue and strategy expert growing Storiara's market presence and building partnerships with filmmakers and studios worldwide.